File #: RES 10382   
In control: City Council Regular Meeting
On agenda: 4/23/2024
Title: Resolution authorizing execution of Change Order 1 to increase the construction contract with Cornerstone General Contractors, Inc. (Bid No. 21022) by an amount not to exceed $2,345,960, plus all applicable taxes, for a contract total amount not to exceed $34,579,270, plus all applicable taxes, for the Fire Station 10 Project (CIP Plan No. PS-64).
Attachments: 1. Agenda Memo, 2. A. Vicinity Map, 3. B. CIP Project Description PS-64, 4. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Resolution authorizing execution of Change Order 1 to increase the construction contract with Cornerstone General Contractors, Inc. (Bid No. 21022) by an amount not to exceed $2,345,960, plus all applicable taxes, for a contract total amount not to exceed $34,579,270, plus all applicable taxes, for the Fire Station 10 Project (CIP Plan No. PS-64).