File #: 23-698   
In control: City Council Regular Meeting
On agenda: 11/6/2023
Title: Motion to reject the bid protest from HCON Incorporated and award Bid No. 23063 for the Water Main Replacement 2022 project to Fury Site Works Inc., as the lowest responsive and responsible bidder, in an amount not to exceed $6,059,761.61, plus all applicable taxes (CIP Plans No. W-16 and W-67).
Attachments: 1. Agenda Memo, 2. A. Vicinity Map, 3. B. CIP Project Description
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Motion to reject the bid protest from HCON Incorporated and award Bid No. 23063 for the Water Main Replacement 2022 project to Fury Site Works Inc., as the lowest responsive and responsible bidder, in an amount not to exceed $6,059,761.61, plus all applicable taxes (CIP Plans No. W-16 and W-67).